Distribution network design and utility approval

15, 25 and 35 kV networks, from routing to approved submission.

A land development waiting for network approval is capital standing still.

We design overhead and underground distribution networks in all three voltage classes and manage the process through utility approval.

Specialized experience

The team’s experience includes distribution-network analysis and design for RGE/CPFL, as well as Maccari’s own contracts. It includes three engineers, each with more than seven years of experience in 15, 25 and 35 kV networks.

The work covers land developments, overhead and underground networks, utility-outlet poles, pole-mounted substations, network extensions and technical support through approval.

What we design

  • 15, 25 and 35 kV overhead distribution networks
  • Underground distribution networks
  • Electrical design for land developments, including street lighting
  • Utility-outlet poles
  • Pole-mounted substations
  • Network extensions and feeder reinforcement
  • Incoming power and metering
  • Management and supervision of network construction
Featured topic

Experience on the other side of the submission desk

Members of the technical team spent seven years at RGE reviewing projects. Their work included receiving submissions, checking compliance with utility standards and assessing them for approval or return with requirements.

That experience changes what leaves our office. The project is prepared in the format reviewers expect, with the details that commonly trigger requirements resolved before submission. This is not a promise of faster approval; it is the knowledge of a team with experience on the other side of the desk.

Featured topic

Approval

The drawing is rarely what holds a project up. Small deviations from utility standards can cause a rejection and send the process back by weeks.

We deliver the design in the required standard and follow the review to completion, responding to requirements as they arise. You do not have to mediate between the designer and the utility.

WHAT YOU RECEIVE

  • Utility-compliant project ready for submission
  • Design report and calculation memorandum
  • Route drawing with poles, structures and crossings
  • Sizing of conductors, transformers and protection
  • Street-lighting design
  • Bill of materials following utility standards
  • ART issued

SIZE RANGES

RangeScopeTypical schedule
Up to 50 lotsDistribution network and street lighting. Incoming power and metering.20 business days to submission
50 to 200 lotsComplete network with transformation. Street lighting and protection. Support throughout approval.25 business days to submission
More than 200 lotsNetwork with multiple feeders. Voltage-drop and power-flow studies. Coordination with urban planning. Construction supervision.35 business days to submission

These schedules cover preparation of the project for submission. The utility has its own review period, which Maccari monitors through completion.

Applicable standards

NBR 14039, NBR 5410, NBR 15688 and NBR 5101, plus the standards of RGE, CEEE Equatorial, Celesc, Copel, CPFL Paulista and Enel, according to the project region.

Next step

Send the urban development plan and number of lots. We will reply within one business day with scope, schedule and price.

Request a quote
How it works

A CLEAR PROCESS FROM FIRST CONTACT TO DELIVERY.

01

You describe

Describe what you need through the form or WhatsApp, including size and deadline. Attaching a drawing speeds up the process.

02

Technical consultation

We reply within one business day for a short technical conversation to define scope and verify applicable requirements.

03

Proposal

We send a proposal stating inclusions, exclusions, price and schedule.

04

Delivery

We deliver with the ART issued.

Who signs

IDENTIFIED TECHNICAL RESPONSIBILITY.

Every project and technical report issued by Maccari is signed by a qualified professional registered with the appropriate professional council, with an ART or TRT duly filed. You know who is technically accountable before hiring us and after delivery.

The technical team includes electrical engineers, occupational safety engineers and electrotechnical technicians, with consolidated experience in 15, 25 and 35 kV networks.

Every stage has a designated technical professional

From survey to commissioning, responsibility is registered in the name of the professional who performed the work.

Frequently asked questions

DIRECT ANSWERS.

Yes. We work throughout Brazil and have delivered projects in RS, SC, PR, SP, MS and MG. Travel is itemized in the proposal.
Yes. Every project and report includes an ART issued in the responsible engineer’s name.
Most reports are delivered within 10 business days after inspection. Industrial facility projects take 10 to 20 business days depending on capacity, and network projects take 20 to 35 depending on the number of lots. The PIE takes 30 business days, while a power quality report takes 15 to 20 because it includes the seven-day PRODIST measurement campaign. Every proposal includes a firm delivery date.
Yes, if you want us to. The construction quote is presented later and separately from the design or report. You remain free to hire any contractor.